Technical Supervision of Concrete Pumps — TDT Inspections

TDT inspection of a silo trailer — pressure vessel check

Key takeaways

Technical supervision of concrete pumps — required for all pumps with pressure vessels (Putzmeister, Cifa, Schwing, truck mixer pumps). PHS Magnum provides service and preparation for TDT inspections with TDT-M/N-19/22 authorisations valid until 14.04.2030.

TDT elementTypically
Periodic inspectionEvery 2-4 years
Ad-hoc inspectionAfter a major repair
TDT decisionValid until the next inspection
Inspection bookUpdated after every operation
Inspection preparation1-2 working days
Inspector attendance0.5-1 day

TDT phone (Roland Sobota): +48 504 788 385
Service phone: +48 602 716 551


What is subject to technical supervision on concrete pumps

A concrete pump as a machine consists of several systems — TDT covers specific components, not the whole machine:

Material hopper

  • The hopper receiving concrete from the mixer
  • Agitators inside the hopper (if fitted)
  • The access safety grate

The pumping system (high pressure)

  • Pumping cylinders (the main component)
  • Pump pistons
  • Pump valves (ball or S-valve)
  • The hydraulic drive system (>250 bar as standard)

Pipelines and fittings

  • High-pressure pipelines from the pump to the delivery end
  • Overpressure safety valves
  • Couplings, elbows, pressure bends

The boom (masts of truck-mounted pumps)

  • The steel boom structure
  • The hydraulic motion connections
  • The control mechanisms (proportional, manual)

Truck mixer pump — additionally

  • Mixing drum — steel structure
  • Drum drive (hydraulic or mechanical)
  • Feed chute (if fitted)

Brands we handle

PHS Magnum provides service and TDT supervision for pumps by:

Putzmeister (German premium)

  • BSF (Boom Pump) — truck-mounted pumps with a boom
  • BSC (Concrete Pump Stationary) — stationary pumps
  • Stationary Pumps (P.P. 715, P.P. 715 D-S)
  • Mixers (Putzmeister mixers)

Cifa (Italian premium)

  • K-Series — truck-mounted pumps with a boom
  • Magnum Series — large pumps with 36-58 m booms
  • Cifa MK truck mixer pumps

Schwing (German premium)

  • KVM — truck-mounted pumps
  • S-Lift — stationary pumps
  • Schwing Stetter truck mixer pumps

Others and truck mixer pumps

  • Truck mixer pumps: Sany, Zoomlion, Kobayashi, Polish KIT
  • Small stationary pumps (Putzmeister BSA, IMER, Carmix)

The TDT inspection preparation procedure

Step 1: TDT date and notice (3 months ahead)

PHS Magnum reminds clients of the upcoming inspection 3 months in advance. The client books a workshop slot.

Step 2: Pre-inspection check (1-2 days)

At the Chorula workshop:

  • Diagnosis of all pressure components
  • Hydraulic pressure test (usually 1.5× MOP)
  • Inspection of the vessel welds (PT or UT)
  • Safety valve check (actuation test)
  • Review of the historical documentation (inspection book)
  • Verification of compliance with the supervisory decision

If the check reveals necessary repairs (seals, minor cracks, a safety valve) — PHS Magnum carries them out before the inspector attends.

Step 4: Notifying the TDT inspector (2-3 weeks)

We report the pump ready to TDT. The queue for an inspector is typically 2-3 weeks depending on the region.

Step 5: Inspector attendance (0.5-1 day)

At the Chorula workshop:

  • The TDT inspector carries out the inspection
  • Repeated pressure tests (with documentation)
  • Non-destructive weld testing (if required)
  • Issue of the TDT decision

Step 6: Documentation and handover

  • Entry in the inspection book
  • The supervisory decision handed to the client
  • Stamp/seals on the vessel
  • The pump ready for further operation

Pump repairs that require TDT authorisations

The following repairs REQUIRE TDT-M/N authorisations:

  • Welding of the material hopper
  • Welding of high-pressure pipelines
  • Replacement of safety valves
  • Modernisation of the hydraulic system (pressure change)
  • Replacement of pipeline sections
  • Boom repair (welding of the load-bearing structure)

PHS Magnum holds decision TDT-M/N-19/22 (amended T.5900.63.2026.T22.1, valid until 14.04.2030) — authorisations for all the operations above.

Without this decision, a workshop may only carry out:

  • Minor repairs not touching the pressure components
  • Replacement of consumable parts (filters, oils)
  • Electrical and lighting repairs

That is a fundamental difference — before choosing a workshop, check whether it holds TDT-M/N authorisations for pumps.

Consequences of no valid TDT decision

On site

  • Operation halted by a labour or road inspectorate check
  • Fines for the pump operator
  • Removal from the site by the general contractor

After an accident

  • Criminal liability of the operator (Art. 220 of the Polish Criminal Code)
  • Refusal of insurance payout for damages
  • Civil claims from injured parties

Reputational

  • Blacklists of general contractors
  • Exclusion from large infrastructure projects
  • Loss of government contracts

Standing agreements for pump operators

Pump operators with 3+ pumps in their fleet get:

  • An inspection schedule planned 6-12 months ahead
  • A dedicated technical account manager
  • A fixed contract rate for inspection preparation
  • Workshop priority — a slot reserved in advance
  • Technical consultations by phone

The full service portfolio for concrete pumps lives on a separate domain:

pompydobetonu.pro — Putzmeister/Cifa/Schwing service, spare parts, mobile service, technical blog.

Contact

TDT supervision of concrete pumps — coordinator:

📞 +48 504 788 385 (Roland Sobota — TDT)

📧 biuro@magnumchorula.pl

Workshop address: ul. Kościelna 9, 47-316 Chorula, Poland
4 km from the A4 Gogolin junction

TDT authorisations: TDT-M/N-19/22 (amended T.5900.63.2026.T22.1)
Valid: until 14.04.2030


Related: TDT inspections — all equipment · TDT inspections of concrete pumps and truck mixer pumps · Concrete pump service · Pasternak.me: TDT/UDT/WDT — a guide

DEKRA ISO 9001:2015 Quality Management Certificate — PHS Magnum

ISO 9001:2015

4 km from the A4 Motorway

180 km from German border

Call Email
Pogotowie Techniczne TIR & SILO +48 602 716 551